07:30 Continue anteroom
15:30 Done for today
Current status:
- Bathroom: finished, ceiling has to be painted at edges, new radiator will be installed in 3 to 4 weeks
- WC: finished
- Kitchen: finished, wall tiling will be done by the end of Feburary
- My room: finished, except for curtains and lamp
- Sandra’s room: will be finished by tomorrow, except pliths, will be finished by the end of next week
- Anteroom: finished, furniture will be assembled tomorrow
- Living room: finished
- Dining room: finished
- Bedroom: finished, still needing some shelves














Ähnliche Einträge
- New Apartment, Day 13: Continue Bathroom, WC, Anteroom, Odds And Ends
- New Apartment, Day 12: Complete Moving, Continue Bathroom, WC, Anteroom
- New Apartment, Day 11: Partial Moving, Continue Bathroom, WC, Anteroom
- New Apartment, Day 10: Continue Bathroom, WC, Anteroom, Kitchen, Partial Moving
- New Apartment, Day 8: Continue Bathroom, WC, Finish Kitchen, Lay Pliths, Mount Curtain Rails
- New Apartment, Day 14: Finish Bathroom, WC, Start Sandra’s Room
- New Apartment, Day 9: Continue Bathroom, Partial Moving
- New Apartment, Day 6: Partial Cleaning, Continue Bathroom
- New Apartment, Day 1: Hand-Over Of Keys
- Apartment Update
- New Apartment, Day 16: 99% Done
- New Apartment, Day 7: Buy Curtain Rails, Plinths
- New Apartment, Day 5: Continue Paint Job, Bathroom, WC
- New Apartment, Day 4: Continue Paint Job
- New Apartment, Day 3: Continue Paint Job, Contiune Floors, Prepare Bathroom, Toilet